Demand Survey for various GIDC parks has been made live.

Application For Drainage Connection

Drainage Connection

  • Application Form
  • Documents Checklist
    • The following documents should be kept ready and submitted along with the duly filled up application form of Drainage Connection.
      • Editable application form (Adhesive stamp of Rs. 300)
      • Copy of Offer cum Allotment letter
      • Copy of Approved Building Plans with letter
      • Copy of Licence Agreement / Form of Agreement
      • Approved primary ETP/STP plan by GPCB and certificate of installation
      • If Industrial unit - Copy of GPCB NOC + Copy of application made to GPCB
      • Water supply connection details (location of connection, quantity, size of connection etc.)
      • Water supply bills – Last 3 months (not mandatory)
      • Possession Receipt and /OR Final Transfer Order (Mandatory)

    Note : If necessary, GIDC will ask the applicant to submit other necessary documents to process the application.

  • Scrutiny Procedure

The following verification is carried out by GIDC before providing approval and connection to applicant

  • If building plan is approved
  • Whether quantity applied for same in License Agreement/ Form of Agreement, GPCB NOC and mentioned in the application
  • If difference, then what is the reason (A query may be raised to the applicant in such case)
  • Scrutiny of NOC from GPCB
  • Verify that drainage connection can be given from the existing drainage line on facing road at distance
  • Whether allottee has been allowed to use treated water into garden or any other use/recycling/another disposal
  • Visits the site to fix the location of drainage chamber, verify the free fall arrangements in drainage connection chamber
  • Provides schematic diagram of connection from drainage mains to connection chamber, size of connection, and calculation of drainage connection charges, deposits, contribution charges to applicant

Note : Ideal time for processing a Drainage application without any queries post physical submission of application form and required documents at respective DEE office is as below.

No. Process Ideal time
1 Providing approval for connection 10 days from date of application
2 Providing physical connection on site Max 20 days from date of approval application (Provided all the formalities are completed by the Allottee)
Back to top